More on Block G
"G" is the last of the Marina apartments' Oceana blocks to be offered for sale and built. All original plans for the Al Hamara Village indicated six Marina apartment blocks, A-F. G was added later offering purchasers, presumably latecomers, one more opportunity to buy.
This explains why progress on this block far lags the others. In early June 2006 G-block was in a ready state for construction to begin.
08 June, 2006
Two months later, the plot had been further leveled with piling completed.
04 August, 2006
By September the structure is readied for a podium to be built. Each tower sits raised above a podium over a meter in height. The ground floor will rise above the enclosed area pictured below.
09 Septmeber, 2006
The metal rebar will be encased in the structure's podium.
09 September, 2006
The ground floor will rise above the level pictured.
09 September, 2006
Approximated sea-view from ground floor level of G block.
09 September, 2006
The developer's estimated completion date is May 2007, eight months on.
See progress on all Marina apartment blocks.